JOIN US on Tuesday, June 27, 2023 between 5:30 and 6:30 PM at Trico Electric Cooperative (8600 W. Tangerine Road) for an open house on the Tangerine Road Corridor Improvements project.
About the project
Phase 2 of the Tangerine Road Corridor Improvements will be constructed in two phases in order to address and accommodate planned development in the area.
The western two-and-a-half mile (Phase 2A) from I-10 through Tangerine Business Loop is slated to be constructed first. The start date is estimated for mid-2023. Meanwhile, Phase 2B is in design.
Design elements for Phase 2A include:
Widening of Tangerine Road to a four-lane desert parkway with paved shoulders and a curbed median.
Providing an all-weather roadway that conveys 100-year storm events under the railway through a combination of channels and culverts.
Addition of a 12-foot-wide multi-use-path along the north side of the roadway.
At adonis Road, a signalized intersection and improved access will accommodate future development
A frontage road south of Tangerine Road, providing improved access to Marana Tech Center’s current and future business.
Widening for capacity improvements and pedestrian/bicycle connectivity at the I-10/Tangerine Road Traffic Interchange.