Traffic Update: Pavement Preservation Program - Wade Road

Screen Shot 2018-05-15 at 10.58.56 AM.png

The Town of Marana pavement preservation will continue on Sunday, May 20 through Tuesday, May 22, on Wade Road west of Silverbell Road. Work will also occur on Pima Reserve Road.

On Sunday, May 20, this work will occur during nighttime hours beginning at 8:00 p.m. until Monday, May 21 at 5:00 a.m. No work will occur Monday overnight. 

Daytime hours are scheduled on Tuesday, May 22, 7:00 a.m. through 4:00 p.m.

Expect moving lane closures and lane shifts on work days.

For your safety and that of the contractor’s personnel, please comply with traffic control devices, flagging personnel, and/or detour signs.

Travel time through the project area may increase during construction so please adjust your schedule accordingly. Construction may restrict traffic lanes and create congestion. Taking alternate routes is suggested.

If inclement weather or other events cause delays, the work may be rescheduled without further notice.

Stay up-to-date on Town of Marana news, projects, and events. Visit MaranaAZ.gov, like us on Facebook, and follow us on Twitter.

START DATE:  5/20/2018                                           END DATE: 05/22/2018

DAILY START TIME:  20:00:00                                            DAILY STOP TIME:  5:00:00

SEVERITY: MODERATE

PROJECT CONTACT: For questions related to this specific project, please contact Town of Marana Public Works Office at (520) 382-2536.

Travel Impact:  Light delays