Ina Road Beautification Project update

Landscape work on Ina Road will conclude at the end of March.

Landscape work on Ina Road will conclude at the end of March.

The Town of Marana’s Ina Road Beautification Project is nearing completion. This project has been done in conjunction with the Arizona Department of Transportation’s Ina Interchange Project in an effort to improve portions of Ina Road not part of the ADOT project, including road resurfacing, safety improvements, and landscaping.

Provided is a synopsis of events that will be occurring on Ina Road and Aerie Road in the next two months. Please note that the dates provided are subject to change due to inclement weather conditions.

Landscaping:
Ina road landscaping west of Thornydale is nearing completion. Landscaping crews will begin work east of Thornydale beginning the week of March 11 and is anticipated to last until the end of March. Final rock mulch will be added west of Thornydale on March 19 and east of Thornydale at the beginning of April.

Mill and pave:
Milling work will begin on Town of Marana roads north of Ina Road on March 18 through March 21. Milling on Aerie Road will start March 25 and is expected to last for two days.

Paving will begin on Aerie Road on March 28 then proceed to all Town of Marana roads north of Ina Road beginning on April 11.

Ina Road mainline final pave will begin on April 22 and is anticipated to last through April 26. Expect heavy traffic delays during Ina road paving. Expect two weeks of localized lane restrictions for lane striping and utility adjustments after the completion of the final pave.

Street lights:
Streetlight pole installation will begin the week of May 20 and is expected to last for three weeks. The installation of the poles will involve limited lane closures in isolated areas. Traffic impacts are expected to be minimal.

Traffic signals:
Installation of hardware to ensure proper functioning of the traffic signals will begin at the Ina – Thornydale, Meredith and Oldfather intersections on March 25th through April 4. Expect daytime lane closures and shifts during work hours only.

Celebration:
Join the Town of Marana on May 4 at the Lowe’s Home Improvement Parking Lot for the kick-off ceremony for Ina Road Celebration Weekend. The event will feature a cake cutting ceremony and business festival.